Two network paths to storage do not guarantee that training continues when one path fails. Verify that the client sees both routes to the same namespace, how it selects a usable path and what happens to the application while access is restored. Linux NVMe multipath considers ANA state and a path-selection policy; end-to-end behaviour also depends on the array, network, filesystem and timeouts.

This guide focuses on failover and recovery, not a price comparison of local NVMe and network storage. Simulate failures only in an agreed window using recoverable test data and a documented rollback procedure.

Understand the path

One namespace can be reachable through multiple controllers or connections. The Linux kernel NVMe multipath documentation describes combining paths with the same namespace identifier into one block device and selecting a route for I/O. The client and storage system need compatible support and configuration.

Asymmetric Namespace Access, or ANA, reports the access state of a path. Linux documentation says an optimized path is preferred when one is available. A connected path alone does not establish that application latency or bandwidth meets a service objective.

Obtain a diagram of client ports, cables, switches and storage controllers. Two software connections sharing one cable still share that cable as a failure point. Multiple controllers with a common unprotected power input can share a power failure. Independence must be evaluated against the real topology.

Establish the baseline

Record kernel, utilities, drivers, transport, client and array settings, namespace and controller identifiers, selected policy and current path states. Linux documents numa, round-robin and queue-depth policies; check availability and behaviour for the deployed version.

Verify that both routes refer to the intended namespace rather than different volumes with similar names. Preserve timeouts and reconnection settings. Do not change them on a production cluster without a compatibility review and approved rollback.

Map shared components and identify exactly which element each proposed failure test will exercise. This avoids calling two routes independent when they share a switch, controller, power feed or management dependency.

Define success for the application

An operating-system path becoming available is not the same as the AI job successfully continuing. The application can have its own I/O timeout, open files and retry behaviour. Agree the permitted pause, error criteria, data-integrity checks and recovery procedure before testing.

For an illustrative service, suppose the permitted I/O pause is 15 seconds and the application timeout is 20 seconds. A hypothetical 12-second failover meets both timing thresholds; 18 seconds stays below the application timeout but violates the service objective. These numbers are examples, not recommended settings or measurements.

For checkpoint writes, verify the resulting data can be read and used after failover. Restored network connectivity alone does not prove the checkpoint was complete.

Run a controlled exercise

Use an isolated test namespace and recoverable data. Agree the people, maintenance window, failure method, stop criteria and restoration plan. Confirm backups and management access first. Do not disconnect an arbitrary port in a shared production fabric for an experiment.

Run representative read or write I/O and record latency and errors. Capture both path states, then have the responsible administrator perform the agreed single-path failure. Record the event time, client and array response, application errors and time until useful I/O resumes.

Restore the route and verify the expected state and policy. Test the other independent path only after the first is healthy. A cable failure does not cover controller, switch or power failures; test those separately only when included in the design and approved procedure.

Measure the complete chain

Build a timeline from client, network, storage and application. Record latency, throughput, error counts, failover duration and the time until training continues. If timestamps differ, check clock alignment and measurement boundaries.

Suppose eight GPUs wait 30 seconds for data during one hypothetical failover. Waiting time is 8 × 30 / 3,600, or approximately 0.067 GPU-hours. This is an arithmetic illustration, not a measurement or loss estimate. Track repeated events and lost work separately.

Compare one-path and two-path operation under the agreed workload. Two routes do not automatically double throughput: policy, ANA state, shared controllers and network limits can change the result.

Verify return to normal operation

After restoring a path, confirm that the client sees the controller, its state matches the policy and the application no longer receives errors. Check the filesystem and completion of pending work under the supplier's procedure. Some implementations move traffic back to a preferred route; measure any second pause instead of assuming the return is invisible. Repeat observations for each critical client, since versions and routing can differ.

Document acceptance

Record the topology, versions, policy, path states before and after failure, workload, actual pause, errors, data-integrity checks and restoration steps. If the application stops, separate the observed symptoms from unproven explanations.

Include recovery time, data availability and latency objectives when selecting GPU servers and storage. Review server selection or contact AI Server Lab. Compatibility and commercial terms must be confirmed for the actual devices and software.