A server booting successfully does not prove that the delivered system matches the order or can sustain the intended workload. Agree on acceptance criteria before delivery: identification, hardware diagnostics, topology, thermal behavior, application checks, evidence and the process for resolving failures.

The procedure should match the exact server, vendor manuals and site rules. Do not run intrusive stress tests on a production workload or exceed the manufacturer's electrical and thermal limits.

Agree on the evidence before delivery

Compare the signed bill of materials with the delivery note: server and GPU models, quantities and serial numbers, CPUs, installed memory, storage, NICs, power supplies, software licenses and accessories. Record discrepancies and whether a substitute part was authorized. Photograph packaging or visible damage according to the carrier's claims procedure, without exposing sensitive identifiers unnecessarily.

The contract should specify test duration, versions, pass and fail thresholds, environmental conditions and who is responsible for remediation. Avoid a vague promise that equipment will be 'fully tested': define the measurement and the party that signs the result.

Identify devices and check basic health

Record firmware, BIOS, management controller, driver and operating-system versions. Use the OEM's supported inventory tools to confirm GPU count and identifiers, memory modules, drive health and power supply status. Check system and management logs for errors before and after each run. Compare network ports and negotiated speed with the agreed design.

For NVIDIA systems, nvidia-smi documentation explains device queries and telemetry. AMD and other accelerators require their own supported tools and version-specific documentation. A single tool's green status is not a complete acceptance result.

Validate topology and communication

Compare the observed GPU, CPU, PCIe and NIC topology with the approved system diagram. If the workload depends on inter-GPU links or GPUDirect capabilities, validate the exact data path in the deployed software environment. A physically active link does not by itself establish that the intended application can use it.

Check expected device access from the host, container or virtual machine, as applicable. Record driver and runtime configuration, peer access and representative communication results. If results differ from the expected topology, preserve logs and investigate before accepting the system.

Run an agreed diagnostic and thermal profile

Use diagnostics supported by the vendor, such as NVIDIA DCGM diagnostics where applicable, and an agreed workload duration. Monitor input power, temperatures, clock limits, cooling, error counters and throttling against the manufacturer's limits. For liquid-cooled equipment, the qualified site team should verify flow and leak-detection conditions according to the OEM instructions.

Different workloads create different heat and communication patterns. A diagnostic that exercises memory is useful but does not replace a representative application run. Define a safe stop condition and do not improvise power or cooling changes to force a pass.

Validate the workload and record the result

Use a fixed model or application revision, software stack, test data and quality threshold. For inference, record concurrency, first-token and end-to-end latency, completed requests, errors and peak memory. For training or HPC, record step or job time and correctness. Capture the test configuration and repeat enough to understand normal variation.

For example, if 495 out of 500 representative requests finish correctly within the agreed interval, the observed completion fraction is 495 / 500 = 99%. Whether this passes depends on the pre-agreed threshold and on how correctness and time are defined. This calculation is illustrative, not a server benchmark.

Finish with a signed report identifying the system, evidence, exceptions, corrective actions and retest responsibility. Agree how firmware changes or component replacements affect the result. Payment timing and remedies depend on the contract and applicable local rules.