At SC26, ASUS showcased the XA AM3A-E13: a 10U air-cooled server with eight AMD Instinct MI355X accelerators. It is an existing ASUS product featured in a current exhibition portfolio, not a newly introduced GPU. The interesting infrastructure question is how its air-cooled design compares with liquid-cooled systems using similar accelerators.

No direct-liquid loop in the stated server configuration does not mean the room can ignore heat rejection. Confirm electrical input, airflow, cooling capacity, rack density and service clearances. A US trade-show showcase does not establish price, stock or delivery conditions in another market.

The configuration ASUS describes

The ASUS SC26 announcement identifies the air-cooled XA AM3A-E13 with eight MI355X GPUs. Its product page lists a 10U platform with dual AMD EPYC 9004/9005 processors, 24 DDR5 DIMM slots, up to 11 PCIe 5.0 expansion slots and ten 2.5-inch drive bays.

These are platform capabilities, not a guarantee that every quoted system includes all components. Confirm CPUs, memory population, networking, drives, controller requirements and support for the specific SKU. Some options can depend on revision or configuration.

GPU memory and workload placement

AMD lists 288 GB HBM3E and up to 8 TB/s peak memory bandwidth for each MI355X. Eight devices therefore have 2,304 GB, or 2.304 TB decimal, of nominal aggregate memory. This is memory on separate accelerators, not an automatic single local pool for any application.

A model distributed across devices needs a compatible runtime and communication scheme. Account for weights, request cache, libraries and buffers. Independent replicas must each fit in their assigned GPU or supported device group.

As an illustrative budget, 190 GB of weights plus 35 GB of cache and 20 GB of buffers totals 245 GB before additional reserve. That is not an ASUS measurement or proof that a particular model fits. Measure peak use with the actual model format, runtime, context and concurrency.

What 10U means in a rack

Four 10U chassis would occupy 40U of a nominal 42U rack, leaving a 2U arithmetic difference. This does not prove that four units fit: networking, power distribution, depth, mass and service clearance may constrain the design. Ask for the actual rack drawing and installed weight.

Comparing a 4U liquid-cooled server with a 10U air-cooled server by GPU count per U omits important site requirements. Include switches, cabling, service access, air handling, power distribution and any liquid-cooling distribution equipment. Similar GPU counts also do not guarantee equal performance when CPU, memory, interconnect, NIC topology or software differ.

Electrical load and airflow

AMD lists 1,400 W typical board power for MI355X. Eight such values total 11.2 kW for the GPUs alone as arithmetic; this is not a measured or confirmed server input for a particular XA AM3A-E13. CPUs, system memory, storage, networking, fans and conversion losses are additional.

Request the OEM's full-system maximum input, supported power-supply redundancy and facility connection requirements. Have the site engineer verify available circuits and PDU capacity for normal and failure conditions. Summing PSU nameplate ratings is not the same as measuring system draw.

For an example energy calculation, a hypothetical system averaging 14 kW over eight hours would consume 112 kWh at that measurement boundary. The assumed value is not an ASUS specification. Operating cost requires a measured utilization profile, local tariff and any relevant facility overhead.

Ask for inlet temperature and humidity limits, required airflow, direction and permitted backpressure. Check hot-air containment and the room's ability to cool simultaneous workloads. Record inlet and component temperatures, fan behavior, clock limits and input power under an agreed workload and supported conditions. Plan maintenance and recovery if a fan or cooling path fails.

Network and storage planning

Map the data path from storage through the network and host to the GPUs. Confirm the NIC models, socket placement, switch topology and whether optics and cables are included. Listed PCIe slots do not mean adapters are included in a quotation.

As an example, reading a 12 TB dataset in one hour requires roughly 3.33 GB/s of useful average throughput before overhead and competing work. This is arithmetic, not an ASUS benchmark. Measure data-loading time, CPU activity and GPU idle time together, then repeat after correcting the identified bottleneck.

Validate AI performance

Fix the model and data revision, precision, ROCm, driver and framework versions and the quality criterion. For inference, measure first-token and end-to-end latency, throughput and errors at expected concurrency. For training, include step time, effective batch and checkpoint behavior.

Verify GPU, NIC and storage topology for the selected SKU. If the job spans nodes, include the actual network and data path; a single-device or single-server result does not establish cluster scaling. Warm up, repeat and keep configuration logs.

Request the exact bill of materials, electrical and thermal specifications, airflow and rack requirements, supported software, acceptance procedure and warranty. Availability, price, spares and delivery need confirmation for the destination country. For a configuration discussion, visit the AI Server Lab catalog or use the contact form.